What can go wrong in Shipbuilding Contracts?
Contractual risks in shipbuilding projects begin when the parties first make contact. Things that could go wrong at this stage could include disputes on whether a contract or letter of intent is binding. [1]. Also, issues could arise involving breach of confidentiality [2] and intellectual property rights. [3]
Upon the effective date of the contract, the parties may exchange refund and payment guarantees, which could be unenforceable [4], or there may be issues with the option agreement for additional vessels [5].
Throughout the production phase, arguments concerning the approval of plans and drawings could involve the buyer’s delays during the approval process and their comments on the plans and drawings [6]. Other disputes could concern variations, [7] delays [8], quality of workmanship, late inspection [9], over-inspection and interference. All this inevitably could lead to delays, and this will be compounded further if, to win the project, the shipbuilder had created an illusion of on-time delivery by developing a schedule with the completion date as a reference point and working backwards. In such circumstances, any subsequent rush to speed up the project may cause construction shortcomings, thus adding to more delays.
Subcontractors could also join in the fray through disputes concerning shortcomings in quality, workmanship, late completion or late delivery of work and equipment, respectively, and non-compliance with contract specification. As subcontractor’s delays (except for those that are related to buyer supplies) are at the shipbuilder’s risk, any delays caused by their shortcomings above will be at the shipbuilder's expense.
During testing and sea trials, the vessel could be found wanting in performance criteria relating to speed, fuel consumption, deadweight deficiency, and cubic capacity, resulting in liquidated damage and possible termination of contract where performance does not comply with specified allowable margins.
In the event of delayed delivery [10], the buyer will be entitled to liquidated damages and also to terminate the contract after a “drop-dead date” [11]. When this happens, they could encounter allegations that the buyer got the drop-dead date wrong, as some of the delays were due to the buyer’s default, thus the buyer has wrongfully repudiated the contract. [12]. Where the vessel does not comply with the contract specification, the buyer could refuse to accept delivery. Conversely, a shipbuilder could disagree and contend that the buyer's refusal to take delivery of a vessel was totally unjustified.
Even when the vessel is finally delivered, it may be premature to celebrate, as the parties may have to reckon with post-delivery warranty issues.[13]. In cases when buyers or shipbuilders call on the refund and payment guarantee, respectively, they may still face serious technical and legal challenges. [14]
While the majority of shipbuilding disputes are resolved through negotiated settlement, mediation, classification society or expert determination, there are still those that end up in arbitration or the courts. Even at this juncture, there may be challenges concerning jurisdiction or the seat of arbitration [15] and others. In such a situation, the ultimate results could be rather unpredictable. This is particularly so in cases (a) of ambiguity, (b) where judicial decisions remain divided on the correct application of the law [16], and (c) in cases which depend substantially on the judicial interpretation of the text in one or more clauses in the contract.
The journey will be tedious, as such proceedings can last many years, and in one particular case involving a pipelay vessel, about ten years. Ultimately, the effectiveness of enforcing the arbitration award or judgment against the losing party will depend on whether that party is still solvent and, if otherwise, whether there will be enforcement issues in its country of residence.
Yet all is not gloomy if steps are taken from the very beginning to identify, avoid or minimise not only contractual but also technical and other associated risks.
Footnotes
1. RTS Flexible Systems Ltd v Molkerei Alois Muller GmbH & Co. KG [2010] UKSC 14.
2. Seager v. Copydex [1967] 2 All ER 415. Saltman Engineering Co. Ltd v Campbell Engineering Co. Ltd (1948) 65 RPC 203.
3. Salt Ship Design AS v. Prysmian Powerlink SRL [2021] EWHC 2633 (Comm).
4. See footnote 14, infra.
5. Haugland Tankers v RMK Marine [2005] EWHC 321 (Comm).
6. Cenargo Ltd v Empresa v Nacional Bazan de Construcciones Navales Militares SA [2001] EWHC 543 (QB), [2002] EXCA Civ 524 QBD (Comm).
7. McAlpine Humberoak Ltd v McDermott International Inc [1992] CILL 747., Blue Circle Industries Plc v Holland Dredging Co (UK) Limited (1987) 37 BLR 40.
8. Zhoushan Jinhaiwan v Golden Exquisite Inc & 2 others [2014] EWHC 4050 (Comm).
9. See footnote 7, supra.
10. Taking into account permissible and possibly concurrent delays.
11. Stocznia Gdynia Sa v Gearbulk Holdings Ltd, [2009] EWCA CIV 75.
12. Jiangsu Guoxin Corporation Ltd (Formerly Known as Sainty Marine Corporation Ltd) v Precious Shipping Public Co. Ltd [2020] EWHC 1030 (Comm). Note also, Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm), where the shipbuilder unsuccessfully invoked the prevention principle.
13. Neon Shipping Inc v Foreign Economic 7 Technical Corporation Co. of China and others [2016] EWHC 399 (Comm).
14. CIMC Raffles Offshore (Singapore) Limited and Yantai CIMC Raffles Offshore Limited v Schahin Holding [2013] EWCA Civ 644., Rainy Sky S. A. v Kookmin Bank [2011] UKSC 50, [2010] EWCA Civ 582., Sea-Cargo Skips As v State Bank of India [2013] EWHC 177., Wuhan Ocean and Nantong v Schiffahrts-Gesellschaft [2012] EWHC 3104 (Comm)., Meritz Fire and Marine Insurance Co Ltd v (1) Jan de Nul NV and(2) Codralux SA [2010] EWHC 3362 (Comm), [2011] EWCA Civ 827., WS Tankship II BV v Kwangju Bank Ltd [2011] EWHC 3103., Carey Value Added SL v Grupo Urvasco SA 2010 EWHC 1905 (Comm), Sea Emerald SA v Prominvestbank [2008] EWHC 1979 (Comm)., Stocznia Gdynia SA v Gearbulk Holdings Ltd [2008] EWHC 944 (Comm).
15. Sulamerica Cia Nacional De Seguros S.A. and others v Enesa Engenharia S.A. and others [2012] EWCA Civ 638.
16. Especially in consequential loss, refund or payment guarantees, and delays claims.