Shipbuilding Contracts - COVID-19 and Excessive Delays
In an ideal scenario, shipbuilders will be entitled to relief because of the impact of COVID-19 provided they fulfil the following conditions;
(a) Quarantines, epidemics, pandemics, infectious disease, requirements of governmental
authorities, shortage of supply and manpower, for example, are covered in the
force majeure clause of their shipbuilding contracts, (b) Shipbuilders have done
everything right and comply with notice requirements in the force majeure clause
to gain protection, and (c) Shipbuilders has done everything possible to
mitigate such delays.
However, such relief will only be temporary if the delays are
protracted as the buyer may still have the right to terminate the shipbuilding contract
for excessive delays.
Bimco NEWBUILDCON. Clause 39(a) Buyer’s Termination, The Buyer shall have the right to
terminate this Contract forthwith upon giving notice in the event that (iii) (1)
the delivery of the Vessel is delayed by more than 180 days by virtue of events
that fall within Clause 34(a) (i) (Permissible Delays - Force Majeure events);
or (2) the delivery of the Vessel is delayed by more than 180 days by virtue of
events which do not fall within Clause 34 (a) (i) or Clause 34(a) (ii)
(Permissible Delays); or (3) the
aggregate of delays to the delivery of the vessel in (1) and (2) above is more
than 270 days.
SAJ Article VIII.4. Right to Rescind for Excessive Delay. If the total accumulated time of delays on
account of the cause specified in Paragraph 1 of this Article, excluding delays
of a nature which under the term of this Contract permits postponement of the
Delivery Date amount to Two Hundred and Ten (210) days or more, then, in such
event, the Buyer may rescind this Contract…” (Paragraph VIII.1 contains a list of force majeure
events).
In such an event, shipbuilder will have to refund all sums
paid with interests and return or pay for buyer’s supplies under Bimco NBC,
Clause 39 (e) or under SAJ Article X.2, refund all sums paid by the buyer, with
interests.
The deciding factor on who wins all will be market-driven.
If the charter for the vessel is still open or if the vessel is a tanker, the situation may not be too bad for such shipbuilders. With potential legal wrangling looming,
the ultimate winners in this saga will still be the shipbuilding litigation lawyers,
claim consultants and the court-appointed receivers.
Comments