Shipbuilding Delays & Extension of time
“… delays in construction are prima facie the
responsibility of the Builder, unless they are excused by a provision of the
contract.”. Per Leggatt J at para 68.
In the case of Zhoushan Jinhaiwan v Golden Exquisite Inc & 2 others [2014] EWHC 4050 (Comm), Buyer cancelled the
shipbuilding contracts as delivery of the vessels were delayed more than 270
days after the delivery date. Shipyard argued that the cancellation was
wrongful as some of the delays was caused by Buyer’s own breach of contract which
amounted to a repudiatory breach. On appeal from two arbitrations, Mr Justice Leggatt
identified three types of delays in the contract. They were permissible delay, non-permissible delay and excluded delay.
Non-Permissible Delay
Under Article III.1 (b) of the contract Buyer could deduct a specified sum from the final instalment for each day that the delivery of the vessel was delayed by more than 30 days but less than 210 days after the Delivery Date specified.
Under Article III.1 (b) of the contract Buyer could deduct a specified sum from the final instalment for each day that the delivery of the vessel was delayed by more than 30 days but less than 210 days after the Delivery Date specified.
Permissible Delay
Under Article VIII, the delivery date of vessel will be extended if Shipyard is affected by certain stated events or other causes beyond its control, provided notice is given within 7 days its commencement and cessation respectively. In the absence of such notice, Shipyard will be barred from any relief claimed.
Under Article VIII, the delivery date of vessel will be extended if Shipyard is affected by certain stated events or other causes beyond its control, provided notice is given within 7 days its commencement and cessation respectively. In the absence of such notice, Shipyard will be barred from any relief claimed.
Excluded Delay
Even though not expressly named as such in the contract, the Judge described the following delay events that provide for an extension of the delivery date as Excluded Delays: (a) Changes in the specifications, plans class requirements, Articles V.1 and V.2, (b) Late delivery of Buyer’s supplies, Article V.4, (c) Failure of the Buyer’s representatives or supervisor to attend sea trials, Article VI.1, (d) Buyer’s default in (i) payment of instalment, (ii) failing to provide a guarantee of payment or (iii) failing to take delivery of the vessel under the contract, Article XI.4(a), (e) Mutual agreement by the Parties to proceed with the contract in the event where the vessel becomes a total, Article XII.2 (b), (f) In event of any arbitration between the Parties, Article XIII.7
Even though not expressly named as such in the contract, the Judge described the following delay events that provide for an extension of the delivery date as Excluded Delays: (a) Changes in the specifications, plans class requirements, Articles V.1 and V.2, (b) Late delivery of Buyer’s supplies, Article V.4, (c) Failure of the Buyer’s representatives or supervisor to attend sea trials, Article VI.1, (d) Buyer’s default in (i) payment of instalment, (ii) failing to provide a guarantee of payment or (iii) failing to take delivery of the vessel under the contract, Article XI.4(a), (e) Mutual agreement by the Parties to proceed with the contract in the event where the vessel becomes a total, Article XII.2 (b), (f) In event of any arbitration between the Parties, Article XIII.7
Cancellation Rights
The contract expressly provided that the Buyer could cancel the contract under the following circumstances:
The contract expressly provided that the Buyer could cancel the contract under the following circumstances:
(a) the
delay in the delivery of the vessel continued for a period of at least 210 days, and/or
(b) If
the total of all accumulated permissible delays is two hundred and twenty five
(225) days or more, or the combination of all permissible and non-permissible delays
is two hundred and seventy (270) days or more.
Excluded
delays did not counted as delays for the purpose of any right of cancellation
as there was no contractual provision that state otherwise.
Under
Article IV, the BUYER undertook and assured that its Supervisor would carry out
his inspections “in accordance with the agreed inspection procedure and
schedule and usual shipbuilding practice and in a way as to minimize any
increase in building costs and delays in the construction of the VESSEL.”
The
Shipyard alleged inter alia that Buyer was in breach of the above undertaking
as the Buyer’s Supervisor worked very short hours, thus delaying the inspection
process and imposed unreasonable requirements, beyond those specified in the
contract, specification, class rules &
regulations, agreed standards and general practices. All these delayed
the construction process.
Also,
the Buyer’s supervisor delayed the return of procedures or drawings of the
vessel and Shipyard could not carry
out further construction of the relevant items. According to the Shipyard such
delay caused by Buyer’s breach was the fourth category of delay. (Note: Notice
of such alleged breach was not given to Buyer and the Shipyard only made the claim
after cancellation of contract).
The Judge pointed out that:
The Yard is only obliged to
correct such nonconformity if it agrees with the Buyer. Buyer’s supervisor has
no power to delay the construction of the vessel. If the supervisor points out what he thinks
is a failure by the Yard to build the vessel in accordance with the contract,
it is up to the Yard to decide whether it agrees with the supervisor, in which
case it must of course correct the defect, or whether it is disagrees with the
supervisor, in which case it is free to ignore him.
Whilst the supervisor had the
right to attend tests and carry out inspections, there was nothing in the
contract which required the Yard to wait for him. Equally, if the supervisor sought to impose
unreasonable requirements beyond those specified in the contract, the Yard had
no obligation to comply with them.
As for returning procedures or
drawings of the vessel (the third form of alleged breach), the specifications
for the vessel were all agreed at the time when the contracts were made and
were annexed to the contracts, and I can see nothing in the contract terms
which required the supervisor’s approval to be sought or obtained for any
procedures or drawings.
The Court
said that there was no additional fourth category of delay and Article IV is
not considered “Excluded delay” as it did not expressly extend the time for
delivery of the vessel due to any breach of Buyer’s undertaking. After considering various arguments from both counsels, the Court held that the delay caused by Buyer’s breach under Article
IV were non-permissible delays. Therefore, such delays could be included in (a)
the period of 270 days’ delay under Article
VIII.3 and the period of 210 days’ delay after the Delivery Date under Article
III.1(c) either of which entitles the Buyer to terminate the contract.
Source:
www.bailli.org
Cases
referred to in the Judgement:
BMA Special Opportunity Hub Fund Ltd v African Minerals
Finance Ltd [2013] EWCH Civ 416 at [24]
Jackson v Dear [2012] EWHC 2060 (Ch) at [40].
Alghussein Establishment v Eton College [1988] 1 WLR 587
Adyard
Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm) at para 255.
The “Kriti Rex” [1996] 2 Lloyd’s Rep 171, 196
Federal Commerce & Navigation Co Ltd v Molena Alpha Inc
(The ‘Nanfri’) [1978] 2 KB 972, 975; Geldof Metaalconstructie NV v Simon Carves
Ltd [2011] 1 Lloyd’s Rep 517 at para 43(vi).
Pioneer Shipping Ltd v BTP Tioxide Ltd (‘The Nema’) [1982]
AC 724, 742.
Some thoughts:
Failure
to serve Notice of alleged Buyer’s breach – Was there a proper contract
management team at Shipyard? If notice has been served, perhaps Buyer’s Senior
Management would have taken notice that all was not well in the Project.
Unless...
Unreasonable
Representatives: Some contract provides for removal of Buyer’s Supervisor or Shipyard’s
Project Manager on account of unreasonable behavior.
Inspection
process – Some contract provide for deemed acceptance if Buyer’s representative
fails to attend schedule inspection & tests. Regardless, most contract will
provide that at the end of the day it is still Shipyard’s duty to ensure the
timely delivery of a seaworthy ship that complies with contract and
specification.
Unreasonable
requirement – As the Judge says, the Shipyard can refuse to comply. What is puzzling
– how is it possible for Supervisor to impose unreasonable requirements in respect of
class items? Prudent contract will provide that in the event of dispute concerning
class requirements, the decision of class shall prevail.
Late
return of procedures or drawings – Most contract will provide that Buyer’s
approval, deemed approval or omission will not diminish Shipyard’s responsibility
to design, construct or deliver a vessel in accordance with the contract and
specification. There should be a specified timeframe for submission of such
documents. If Buyers fails to return such documents with approval, comment, amendments
or reservation, (if any) within the stipulated time, such documents shall be
deemed approved - See NEWBUILDCON Clause
20(e).Should Buyer request for subsequent revision, this could be the
subject of a Variation Order with time and costs impact.
Comments