Shipbuilding - Effective Date of Contract and Contingent Conditions
In shipbuilding contracts, the
parties may occasionally agree that the contact will only become effective
after signing and provided certain contingent conditions are fulfilled. Common contingent
conditions include payment of the first instalment and provision of refund or
payment guarantees. Such contingent conditions may be classified into condition
precedent or condition subsequent.
Condition Precedent - A condition is precedent if it
provides that the contract is not effective until some specified undertakings
are fulfilled. See Article 16 of AWES.
Where a party is required
to do something before the commencement of a contract, there will be no
contract until that condition is met.
Thus in Haugland Tankers v RMK Marine [2005] EWHC
321 (Comm), the term of an Option Agreement provided that Buyer could
exercise the Option by the service of notice together with payment of a
commitment fee to Seller. The Buyer served notice to declare the Option but did
not pay the commitment fee. It was held that simultaneous payment was a
condition precedent to or a requirement for the proper exercise of the Option.
Condition Subsequent - Such condition requires something to be done after the date of
contract which, if not fulfilled will render the contract void. See SAJ Article XIX, Clause 44 Bimco
NEWBUILDCON.
Where contracts are
effective as from the date of execution but
subjected to condition subsequent, communication between the parties must be
carefully managed to prevent possible disputes or litigation.
Thus in Covington Marine Corporation v Xiamen
Shipbuilding [2005] EWHC 2912
(Comm), the parties agreed that a shipbuilding contract shall become
effective from the date of its execution by the parties
provided four conditions were fulfilled. The Seller repudiated the contract
and during the arbitration, the Seller raised jurisdiction issues and denied
that any binding contracts had been concluded. One of the issues on appeal was
whether the parties had reach agreement on the supplier of the main engines.
The Buyers contended that the requisite agreement was achieved by exchange of
letters between the brokers dated 18 and 19 March 2003. However, the
Arbitrators concluded that there was no agreement.
On appeal the Court found
that there was, an agreement on the supplier of the main engine and held that
Arbitrators’ decision and reasoning are wrong in law. But the Court did
commented obiter that it was “an agreement to agree” and that “It would not be
a wrong or a breach of duty not to agree on the supplier of the main engine”.
The problem with contingent
conditions is that it could easily invalidate an otherwise promising
shipbuilding contract from the onset if one of such conditions are not duly
complied with or if communications between the parties subsequent to contract
signing are not properly managed. At times such contingent conditions can be
rather tricky and could be a convenient deal killer when the market condition
worsened.
Some areas of concern:
(a) Where the effective date is dependent
on an “agreement to agree”,
(b) Where the effective date is
dependent upon approval or consent of third parties which may not be
forthcoming or available in a timely manner or impossible to perform,
(c) If Seller’s subcontracts with its vendors are not subjected
to the effectiveness of the main shipbuilding contract, Seller may inevitably
end up with multiple legal suits for breach of subcontracts.
Comments