Shipbuilding - refund guarantees or conditional money back guarantees?
The object of a refund guarantee in shipbuilding is to ensure that Buyer can get their money back (usually from a bank) in the event that the shipbuilding contract is rightfully cancelled by Buyer. However, this assurance at best is tentative as the right to the money is not absolute. Recent examples in shipbuilding cases where call on refund guarantees failed include invalid demand ( Sea-Cargo Skips As v State Bank of India [2013] EWHC 177 ) and lack of authority (actual, ostensible or by ratification) to sign refund guarantees on the bank’s behalf ( Sea Emerald SA v Prominvestbank) . In Sea-Cargo Skips As v State Bank of India , a demand on the refund guarantee issued in connection with a Shipbuilding Contract was held to be deficient. The guarantee required a statement from the Buyer that: “(A) that the vessel or the construction thereof is delayed with more than 270 days as set out in the contract article IV 1 (E) which entitles the buyer to cancel the contract ...